Fire Station 5
Commissioning:5/22/2012
Plant power:43.20 kWp
Communication:Sunny WebBox
Inverter:6 x Sunny Boy 7000US

At Fire Station 5, located in Charleston Heights within Ward 1, panels shade 19 parking spaces. The total size of the system is 30 kW and will generate approximately 60,000 kWh, offsetting the building's meter by about 30 percent. Funding for the project came from New Clean Renewable Energy Bonds and NV Energy SolarGenerations rebates. Contributing to the successful completion of the project was the "design-build" team lead by CORE Construction.